As reported by the City of Nuremberg administration, the Public Space Service has completed the approximately three-month repair work on the Hangman’s Bridge in the old town. Accordingly, as of Monday, November 24th, the historic bridge is accessible for pedestrian traffic again.
Final restoration work on the road surface at the northeastern Unschlittplatz square is expected to be completed by mid-December 2025.
Thanks to the repairs, the covered wooden bridge has not only been preserved for the long term but has also been brought into compliance with modern safety standards, according to the administration.
The light, new wood of the renovated bridge still stands out, but as a natural material, the wood will change over time and gradually acquire a grey patina. This will gradually restore the familiar historical appearance, the administration assured.
The renovation work on the Hangman’s Bridge was previously delayed by approximately four weeks. The reason, according to the City of Nuremberg administration, was the need to carry out two construction phases, originally planned to happen in parallel, sequentially due to structural considerations.
The Hangman’s Bridge, a covered wooden structure from 1954, connects Unschlittplatz square with the Trödelmarkt market. Initial reinforcement measures were already carried out in 2022 to ensure the bridge could be used until the recently completed major renovation.
This recent repair included, among other things:
- Replacing damaged elements in the area of the supports (pier columns) and the main load-bearing structure.
- Restoring or replacing damaged steel components and connectors.
- Renewing the ice breakers.
- Replacing beams that were too weak.
- Increasing the height of the railing from approximately 85 cm to 100 cm in accordance with current standards for pedestrian bridges.
- Installing new railing cladding made of untreated larch wood.
To replace the components, the load-bearing structure was relieved in two construction phases using temporary support structures. Replacing the supports additionally required a temporary, officially coordinated lowering of the water level in the Pegnitz River. The measures undertaken, according to the administration, ensure the long-term preservation of the historic wooden bridge.