Four Munich Metro Lines Returned to Normal Schedule in Time for the Start of Advent

For several months, passengers on the Munich metro switched to buses, waited for shuttle trains and rode past needed stations without stopping.

From 4:00 on Saturday, November 28, lines U3, U4, U5 and have resumed normal service.

As the transport company MVG reported, construction work at several stations was completed just in time for the first weekend of Advent.

Renovation of stations more than half a century old

The main affected lines U3 and U6. Since October 5, the second of three phases of major renovation had been underway at Poccistraße and Goetheplatz stations. Both stations were built in the early years of the metro and are in poor technical condition.

Goetheplatz opened on October 19, 1971, and at the time served as the southern terminus of the first line.

The renovation that has now been completed was intended to address several tasks at once. At Poccistraße, load-bearing structures needed to be reinforced; at Goetheplatz, damage to the structure had to be repaired. In addition, both stations must meet modern safety requirements and become accessible to people with limited mobility.

How trains ran from October

During the second phase, only one track between Goetheplatz and Implerstraße was closed, so service did not have to be suspended entirely.

The operating scheme looked like this:

U3 did not run between Sendlinger Tor and Implerstraße; instead, a bus ran every five minutes;

U6 did not run between Goetheplatz and Implerstraße;

on the section between Implerstraße and Goetheplatz, a shuttle train ran every ten minutes.

Escalators at Max-Weber-Platz

Lines U4 and U5 operated with restrictions for a different reason – two escalators were replaced at Max-Weber-Platz station.

U4 ran in two separate sections: from Arabellapark to Max-Weber-Platz and from Odeonsplatz via Hauptbahnhof to Westendstraße. Lehel station remained closed.

U5 toward Hauptbahnhof and Laimer Platz passed through Max-Weber-Platz without stopping.

Why this matters

The current return to the normal schedule is a breather, not the end of the renovation.

MVG had divided the work at Poccistraße and Goetheplatz into three waves in advance so that trains would run without restrictions during Oktoberfest, Advent and winter.

Normal metro service will last until April 11, 2027.

From April 12, the third and final part of the reconstruction will begin. As in the first wave of work, from May to September 2026, U3 and U6 will not run between Sendlinger Tor and Implerstraße, and buses will again appear on that section. According to MVG’s plan, the renovation of the two stations will be completed in summer 2027.

0 0 votes
Рейтинг статьи
Subscribe
Notify of
0 комментариев
Oldest
Newest Most Voted

Актуальное Blog

Пожалуйста поддержите наш проект: отключите блокировщик рекламы! Именно реклама дает нам возможность оперативно готовить для вас новости. Ваша поддержка помогает нам содержать проект и быть независимыми. Спасибо, что остаетесь с нами!

Don't miss out on other news

0
Would love your thoughts, please comment.x
()
x